Search Guides The competitive flexible procedure, explained: the Procurement Act's new way to tender

The competitive flexible procedure, explained: the Procurement Act's new way to tender

If you bid for UK public contracts, one change in the Procurement Act 2023 reshapes almost every competitive tender you will enter: the competitive flexible procedure. It swapped a menu of rigid, one-size-fits-all routes for a blank canvas the buyer designs themselves — which means no two tenders need look alike. Understanding it is the difference between being surprised by a process and being ready for it.

From five procedures to two

Under the old Public Contracts Regulations 2015, a buyer picked from a fixed set of procedures — open, restricted, competitive procedure with negotiation, competitive dialogue and innovation partnership — each with its own prescribed stages and timetable. The Act sweeps that away. Since 24 February 2025 there are just two competitive tendering procedures:

The government's guidance is blunt about what has gone: "There is no longer a restricted procedure, competitive procedure with negotiation or competitive dialogue procedure but it is possible to adopt a similar approach in practice as part of a competitive flexible procedure." The old shapes did not vanish — they became tools a buyer can assemble at will.

What "flexible" actually means

There is no fixed template for a CFP. The buyer designs a bespoke process — single-stage or multi-stage — to fit exactly what they are buying. They can build in a shortlisting round, a dialogue phase, negotiation, product demonstrations or prototypes, and successive refinements of the tender — or none of these. A CFP for a complex IT transformation might run several rounds with negotiation; a CFP for a simpler service might be barely more involved than the open procedure.

That freedom is the point — and the catch. As a supplier you can no longer assume you know the stages from the procedure's name. You have to read the specific process each buyer has set out.

The rules that keep it fair

"Flexible" is not "anything goes." The Act wraps the freedom in guardrails that protect bidders:

Shortlisting: the one thing only a CFP can do

There is a practical trigger that forces a CFP. A buyer may only limit the field before inviting final tenders — shortlist down to the strongest candidates — under the competitive flexible procedure. The open procedure cannot do this: everyone who bids is assessed. So whenever a buyer wants a "select, then bid" shape, they must use a CFP, applying conditions of participation — proportionate tests of a supplier's capacity or ability — to decide who progresses.

Negotiation and dialogue, when the buyer allows it

A CFP can include negotiation — "the process of aiming to reach a mutual agreement through structured discussion" — typically to sharpen price, quality or contract terms. It "can occur at any stage of a CFP regardless of the number of suppliers," though it usually follows an initial down-selection. Any subject can be negotiated provided it is proportionate and relevant, and every supplier still in the running gets the same opportunity. Crucially, the buyer only has this option if they signalled it in the published procedure — so read the notice for the word "negotiation."

What a CFP looks like in practice

The common shapes you will meet:

Open procedure vs competitive flexible procedure

 Open procedureCompetitive flexible procedure
StagesOne — everyone bidsBuyer-designed: single or multi-stage
Shortlisting before tendersNot possibleYes — via conditions of participation
Negotiation / dialogueNoOptional, if set out up front
Best forClear, well-defined needsComplex, novel or high-value needs
What you must readThe specificationThe specification and the bespoke procedure

What it means for you as a supplier

Three habits protect you under the new regime:

This is exactly the reading Bidvane does for you. For every matching tender it pulls out the procedure, the stages, the deadline and the published selection criteria, then checks them against your profile — so a bespoke, multi-stage CFP arrives as a plain-English brief and a ready-to-bid checklist, not forty pages you have to decode. As always, verify the detail against the official tender documents before you submit; the analysis gets you to the decision fast, it does not replace the pack.

Sources: GOV.UK — Competitive Tendering Procedures (guidance) · GOV.UK — The Competitive Flexible Procedure and Negotiation · Related: The Procurement Act 2023 is live — what changed for suppliers