Pont Dolhendre, Llanuwchllyn
Cyngor Gwynedd · All their open notices
What this is
Replacement of a defective three-pipe armco bridge with a new reinforced concrete single-span beam bridge at Pont Dolhendre, Llanuwchllyn. The work will be executed in two phases to maintain road traffic flow, with all in-river work to be completed by 17 October 2026.
Key points
- Tender deadline: 14 August 2026 at 13:00 (enquiries by 7 August 2026 at 13:00)
- Contract period: 1 September to 17 October 2026; all in-river work must finish by 17 October
- Estimated value: GBP 65,000 (below-threshold open competition)
- Award criteria: 80% price, 20% technical quality
- Electronic submission only via eTender Wales portal (ITT code: itt_126423)
- Two-phase construction required to keep road open to traffic throughout
How it is scored
Quality 20% · Price 80% Price (Commercial): 80%; Quality (Technical): 20%.
Performance guarantee
No performance bond or guarantee requirements stated in the notice.
How to submit
Electronic submission via eTender Wales portal (https://etenderwales.ukp.app.jaggaer.com/home.html) using ITT code itt_126423. Deadline: 14 August 2026 at 13:00.
Clarifications
Enquiry deadline: 7 August 2026 at 13:00. Clarifications to be submitted via eTender Wales portal.
Contract period
Contract period: 1 September 2026 to 17 October 2026 (approximately 6.5 weeks). All in-river work must be completed by 17 October 2026.
Classification
CPV 45000000 — Construction work WalesGwynedd
Published on Sell2Wales. The official notice is the authoritative version.